[Lemon-devel] Network Simplex

Alpar Juttner alpar at cs.elte.hu
Thu Dec 6 15:51:30 CET 2012


On Thu, 2012-12-06 at 14:04 +0100, Kovács Péter wrote:
> Hi All,
> 
> I generally agree with Alpar, but I also agree with Pierre that the 
> distinction between invalid and infeasible is not so clear in this case.
> 
> The min cost flow problem formulation explicitly says that:
>   (a) l(a)<=u(a) must hold for each arc;
>   (b) sum of node supply values must be zero or negative.

No. The doc ( http://lemon.cs.elte.hu/pub/doc/1.2.3/a00005.html ) says
that "The sum of the supply values must be zero or negative in order to
have a feasible solution"

which is exactly what I say.


Regards,
Alpar